Maintenance software for packaging plants
Updated
FleetZap schedules preventive work on packaging lines, records why each line stopped and keeps critical spares such as sealing jaws, knives and belts on the shelf.
Linked lines and lockout during jam clearing
A packaging plant runs long lines of linked machines: fillers, form-fill-seal machines, cartoners, case erectors, labellers, palletizers and stretch wrappers, joined by conveyors. When one stops, the whole line stops. Much of the wear is in small parts (belts, bearings, cutting knives, sealing jaws and suction cups) that need regular inspection and replacement.
Changeovers, short runs and three-shift schedules leave little time for planned work, so a team can clear the same jam on the same cartoner every week with no record of what failed. Failure codes on each repair give the maintenance lead a ranked list of stoppage causes per line, and that list shows which spares to stock and which PM to move up.
Jam clearing is where packaging lines injure people. OSHA’s lockout/tagout standard, 29 CFR 1910.147, exempts minor tool changes, adjustments and other minor servicing during normal production only when the work is routine, repetitive and integral to using the machine, and only when you use alternative measures that give effective protection. If your jam clearing doesn’t meet those conditions, the full lockout procedure applies. Write each machine’s isolation steps into its procedures in FleetZap, with headings and help text, so the night-shift technician follows the same lockout sequence as the day crew.
Weekly jams, postponed PM and missing knives
- Repeat stoppages: The same jam or seal fault comes back every week with no record of the cause.
- PM squeezed by production: Planned work is postponed for another run until a machine fails mid-shift.
- Critical spares missing: A knife, belt or jaw isn’t in stock, so a short repair becomes a long stop.
- Shift handovers: Night-shift fixes and workarounds aren’t passed on to the day crew.
Line assets, cause codes and changeover checks
- PM by run hours or date: Schedule lubrication, belt and knife changes by run hours or calendar for each machine or a whole line.
- Line as nested assets: Set up each line with its machines as sub-assets, so work and cost roll up to the line and each unit keeps its own history.
- Failure codes: Close repairs with a problem, cause and remedy; the failure report shows top problems and repeat offenders.
- Spare parts and reorder points: Keep critical spares listed per machine with live stock; low-stock alerts and purchase orders keep them on the shelf.
- Downtime cost: Set an hourly downtime cost per line or machine and see what stoppages cost month by month.
- Changeover checklists: Build procedures with check, reading, photo and sign-off steps for changeovers and start-up checks.
Fillers, cartoners, labellers and palletizers
- Conveyors
- Filling machines
- Form-fill-seal machines
- Cartoners and case erectors
- Labellers
- Palletizers
- Stretch wrappers
- Forklifts
Planned maintenance share on the line
- MTBF: Low MTBF on one machine in a linked line stops everything behind it; start the cause review there.
- Downtime cost: Price stoppages per line so the cost of a missing jaw or knife shows up when you set the spares budget.
- Planned maintenance %: A falling planned share means crews spend shifts on breakdowns; protect PM slots at changeovers.
- PM compliance: Compliance that drops during long runs shows where the schedule needs a maintenance window.
Free tools for this
- Belt length and pulley calculator: Belt length, driven pulley speed and belt speed for two pulleys
- Roller chain size chart: ANSI roller chain sizes and a chain length calculator in links
- V-belt size chart: V-belt sections, top widths and how belt numbers work
- Horsepower to torque calculator: Torque from horsepower and RPM, and horsepower from torque, in US and metric units
Sources
FleetZap Maintenance
Work orders, PM, parts, compliance, assets and KPIs. Explore FleetZap Maintenance.
Frequently asked questions
Can we track downtime per packaging line?
Yes. Each line or machine is an asset with a downtime cost per hour. Status history records when it was down or back in service, and Reports price that downtime by month. Set the line up as a parent asset and its machines as sub-assets to see cost by line and by machine.
Does FleetZap calculate OEE?
No. FleetZap tracks maintenance KPIs such as availability, MTBF, PM compliance and downtime, built from work orders and status history. It doesn’t read production counts or speeds from your lines, so performance and quality figures for OEE stay in your production system.
Can operators report a fault from the line?
Yes. A QR label on each machine lets operators report a problem with photos from their phone, without an account. The report becomes a request that your maintenance team approves into a work order, already linked to the right machine on the right line.
Can we keep a spare parts list per machine?
Yes. Each asset has a spare-parts list with quantities, shown alongside live stock. When a technician issues parts to a work order on that machine, its listed spares come first in the picker, so the right sealing jaw or belt gets pulled from the shelf.