FleetZap · Features · Solutions · FleetZap Maintenance · FleetZap Rentals · FleetZap Dispatch · FleetZap GPS Tracking · What a CMMS does · GPS tracking & engine hours · Dispatch & route optimization · Rentals module · Industries · Customers · Resources · Free calculators · Free templates · Pricing · Contact

How to calculate the cost of equipment downtime

Updated · Reviewed by Israel Margulies, founder and CEO of High Point GPS

Equipment downtime cost is the number of hours a machine is out of service multiplied by what each hour of downtime costs your business. The hourly figure typically includes lost revenue or production, idle crew time, replacement rentals and any penalties. Repair costs are usually tracked separately.

Downtime cost

Hours of downtime × Cost per hour of downtime

A hypothetical excavator is down 20 hours. Lost billable work is $120 an hour and two idle operators cost $40 an hour each, so $200 an hour: 20 × $200 = $4,000, before the repair itself.

Free tool: Downtime cost calculator: What an hour of a machine down really costs, per breakdown and per year.

What goes into the hourly cost

Agreeing on the cost per hour takes the most effort. Include only the costs that change when this machine stops working. For a rental fleet that is mostly lost rental revenue; for a contractor it is often idle crews and project delays; for a plant it is lost production.

  • Lost revenue or billable hours
  • Wages of operators and crew left waiting
  • Rental of a replacement machine
  • Late-completion penalties or overtime to catch up
  • Knock-on delays to other machines or crews

A worked example

Imagine a hypothetical wheel loader that earns about $150 an hour on a job. When it breaks down, a replacement is rented at $60 an hour and one operator waits at $35 an hour until it arrives. If the loader is down 12 hours and the replacement covers 8 of them, the cost is 4 hours of lost work at $150 ($600), 8 rental hours at $60 ($480) and 4 hours of idle operator time at $35 ($140), or $1,220 in total, plus the repair bill.

Setting a rate per machine or category

You do not need a perfect number for every unit. Many fleets set a downtime rate per category (excavators, loaders, trucks, generators) and override it for machines that are critical or unusual. Review the rates once a year. You use the rate to compare machines and months, so get operations and accounting to agree on it once, then leave it alone until the annual review.

Using downtime cost to make decisions

Put the loader’s $1,220 outage next to the few hundred dollars a preventive service costs and you can show a manager both numbers on one page. Downtime cost also sets the order of repairs: when two machines break the same morning, fix the one with the higher hourly rate first, unless safety says otherwise. Over a year, a machine’s total downtime cost is an important input to repair-or-replace decisions.

Tracking downtime cost in FleetZap

In FleetZap you set a downtime cost per hour on each asset category, and override it on individual machines. Every time a machine goes down or into service, the status change is recorded with a reason, and FleetZap prices that time automatically.

The dashboard shows downtime cost month to date, Reports break it down per machine, and each machine’s downtime tab shows its own history. Combined with cost of ownership (parts, labor, outside repairs and fuel), you see the full cost of keeping each machine running.

Key takeaways

  • Count only costs that change when the machine stops; an operator’s wage counts only while they stand idle.
  • When a rental covers part of the outage, price those hours at the rental rate and the uncovered hours at lost revenue.
  • Set one rate per category and override it only for critical or unusual machines.
  • Keep repair cost separate so you can see whether the outage or the fix drove the total.

Free tools for this

Sources

FleetZap Maintenance

Work orders, PM, parts, compliance, assets and KPIs. Explore FleetZap Maintenance.

Frequently asked questions

Should repair costs be included in downtime cost?

Usually they are tracked separately. Downtime cost measures what you lose while the machine is not working; repair cost is what you spend to fix it. Keeping them apart shows which one is driving the total. For a full picture of a breakdown, add the two together.

What if a machine was not needed while it was down?

Then the real cost of that downtime was low. Some fleets only count downtime during scheduled working hours, or during periods when the machine was booked. Whatever rule you choose, apply it consistently so costs compare fairly between machines and months.

How do I estimate lost revenue for an owned machine?

Use what the machine would have earned or saved. For a rental fleet that is the rental rate. For a contractor it might be the hourly rate you would pay to rent an equivalent machine, or the value of the crew’s work that stopped. A reasonable, agreed estimate is enough.

Does planned maintenance count as downtime cost?

Planned downtime has a cost too, since the machine is not working. Many fleets track it but report it separately from unplanned downtime, because scheduled work can be timed to cost less. The aim is to keep planned downtime short and well timed, and unplanned downtime rare.