FleetZap · Features · Solutions · FleetZap Maintenance · FleetZap Rentals · FleetZap Dispatch · FleetZap GPS Tracking · What a CMMS does · GPS tracking & engine hours · Dispatch & route optimization · Rentals module · Industries · Customers · Resources · Free calculators · Free templates · Pricing · Contact

Construction punch list template

Updated · Reviewed by Israel Margulies, founder and CEO of High Point GPS

A punch list for the end of a job: each item still to finish or fix, where it is, which trade owns it, how urgent it is, when it is due, and who checked it was done.

A punch list is the list of work that doesn’t yet match the contract near the end of a project: a missing cover plate, a scratched door, a fixture that doesn’t work. On AIA contracts, the list of items to be completed or corrected is usually attached to the certificate of substantial completion (G704).

The list closes faster when every item has one trade, one location and a due date. Walk the job with the owner or architect, write items so anyone can find them, and close each one only after it has been checked.

Punch list

Fields: Project name · Project address · Contractor · Owner / architect · Walkthrough date · Prepared by

Log columns: No. · Location (floor / room / area) · Description of item · Trade responsible · Priority · Due date · Completed (date) · Checked by

Fill it in the right way

  1. Walk the job with the owner or architect and the superintendent.
  2. Write each item on its own line with the exact location and what is wrong.
  3. Assign each item to one trade and set a priority and a due date.
  4. Send each trade its items; they mark the date they finished.
  5. Check every finished item before closing it, and sign off the list together.

Tips

  • Start a rolling punch list before the final walkthrough; the last one is shorter.
  • Take a photo of each item and number it the same as the list.
  • Write items so someone who wasn’t on the walk can find them.
  • Keep equipment and tools on site until the trades that need them are done.

Do it in FleetZap

  • Engine hours for each machine can come from FleetZap GPS Tracking or a telematics connection, instead of being written down.
  • With FleetZap Dispatch, pickups of machines from a finished site are planned with the truck, driver, route and ETA.
  • Repairs and costs go on each machine’s history.

Free tools for this

FleetZap Maintenance

Work orders, PM, parts, compliance, assets and KPIs. Explore FleetZap Maintenance.

Frequently asked questions

What is a punch list in construction?

The list of work still to be finished or corrected before a project is complete, usually made at a walkthrough near substantial completion.

Who creates the punch list?

Usually the contractor with the owner or architect at a walkthrough; subcontractors get their own items to fix.

When is a punch list done?

Near substantial completion. Many teams also keep a rolling list through the job so the final one is short.

What should a punch list item include?

A number, the exact location, what is wrong, the trade responsible, a due date, and who checked it was fixed.