FleetZap schedules maintenance for a power plant’s pumps, fans, compressors, transformers and switchgear by run hours or date. Operators record rounds readings on a phone, and planners can see whether a job’s parts are in stock before it comes due.
Balance-of-plant rounds and forced outages
Gas, hydro, biomass, cogeneration and diesel stations each keep hundreds of pieces of balance-of-plant equipment: feedwater and cooling water pumps, fans, compressors, heat exchangers, valves, transformers, switchgear, cranes and backup generators. Most rotating equipment has manufacturer intervals in run hours. Operators also walk rounds and write down temperatures, pressures and vibration readings by hand.
Outages get planned months ahead, and a forced outage means lost generation and a scramble for parts. When rounds readings stay on a clipboard, nobody compares this week’s bearing temperature with last month’s, and a planned job can sit waiting for a spare that was never ordered.
Take a boiler feed pump. On each round the operator reads the inboard and outboard bearing temperatures and checks the seals for leakage. In FleetZap each reading is a step with the high limit from the pump’s manual or your own engineering standard, so a reading over the limit fails the step and opens a repair work order while the operator is still standing at the pump. OSHA’s 29 CFR 1910.269 covers the operation and maintenance of electric power generation equipment, including a station’s fuel and ash handling and its water and steam systems, and your lockout and clearance steps can sit in the same procedure as the repair.
Gaps between rounds, run hours and spares
- Readings on clipboards: Operators write rounds data down, but nobody lines up the numbers, so slow drift goes unnoticed.
- Run-hour intervals: Pump, fan and generator hours sit in several spreadsheets that rarely agree.
- Parts not on hand: A critical spare runs out and the planned job waits on a delivery.
- Contractor work scattered: Vendor reports from an outage arrive as PDFs that never get linked to the equipment.
Rounds, run-hour PM and critical spares
- PM by run hours or date: Schedule service for pumps, fans, compressors and generators by hour meter or calendar, per unit or per category.
- Rounds with readings: Round procedures hold readings with min/max limits. An out-of-range value fails the step, and FleetZap raises a repair work order for that unit.
- Threshold alerts: With a tracker or hand-entered readings, automations can open a work order, mark a unit down or send an alert when coolant temperature or battery voltage crosses a limit.
- Critical spares: Spares get reorder points and low-stock alerts, and purchase orders carry an approval limit. Vendors and stock counts live with the parts.
- Permits and inspections due: Permits, certifications and statutory inspections become compliance items with reminders and automatic inspection work orders.
- Downtime and reliability: Reports cover downtime cost per hour, availability, MTBF and PM compliance, and you can have them emailed on a schedule.
Pumps, fans, transformers and backup generators
- Feed and cooling water pumps
- Fans and blowers
- Air compressors
- Heat exchangers
- Transformers and switchgear
- Backup generators
- Boilers
- Overhead cranes
Forced outage cost and plant availability
- Availability: Availability lost on balance-of-plant equipment shows which pumps or fans need a standby unit or an earlier overhaul.
- MTBF: If MTBF falls on feed pumps, look at the round readings logged before each failure for a slow temperature drift.
- PM compliance: When PM slips, sort the overdue jobs into ones that need an outage and ones crews can finish online this week.
- Downtime cost: Use downtime cost per hour to rank which equipment justifies carrying a critical spare on site.
Free tools for this
- Three-phase power calculator (kW, kVA, amps): kW and kVA from volts and amps, and amps from a kVA load
- Belt length and pulley calculator: Belt length, driven pulley speed and belt speed for two pulleys
- Horsepower to torque calculator: Torque from horsepower and RPM, and horsepower from torque, in US and metric units
- Roller chain size chart: ANSI roller chain sizes and a chain length calculator in links
Sources
FleetZap Maintenance
Work orders, PM, parts, compliance, assets and KPIs. Explore FleetZap Maintenance.
Frequently asked questions
Can FleetZap read our plant control system?
No. FleetZap doesn’t connect to plant control or historian systems. Operators enter readings on rounds or by hand, and mobile equipment can send values from an optional GPS/telematics tracker. Automations then act on those values, for example by opening a work order when a reading crosses its limit.
Can operators record rounds on a phone?
Yes. A round is a procedure with checks and readings. Operators answer it in the field app; answers given in parts of the plant with no signal are saved on the phone and sync when it reconnects, and any reading outside its limits opens a repair as soon as it syncs. The readings stay on the asset’s history.
Can we plan work for an outage?
Yes. Open the outage jobs ahead of time with estimated hours, then lay them out on the calendar and the workload board to see who is overloaded. Check the parts on hand and on order for those jobs weeks before the unit comes offline.
Will FleetZap keep us compliant with regulations?
It tracks the dates. Permits, certifications and statutory inspections become compliance items with reminders and automatic inspection work orders. Proving compliance with any regulation stays with your team and your compliance systems; FleetZap holds the maintenance records you pull from when an inspector asks.