To track equipment downtime, record a timestamp every time a machine stops being able to work and every time it is released back to work, with a reason code and a note on what it was waiting for in between. Kept for a few months, that log tells you which machines lose the most hours, which causes repeat, and how much of each outage was repair work versus waiting.
Downtime percentage
Unplanned downtime hours ÷ Scheduled operating hours × 100
A hypothetical skid steer was scheduled for 176 hours in a month and sat broken for 22 of them: 22 ÷ 176 × 100 = 12.5% downtime.
Decide what counts as down
Write a one-line definition before anyone logs anything, or every technician will use their own. A workable rule for equipment fleets: a machine is down from the moment someone reports it can’t safely do its job until it is released back to work. A machine parked with nothing to do is idle, and stays out of the downtime log. Out for a scheduled service is planned downtime, and you log it too, but in its own category.
The second decision is the clock. Calendar hours are easy to collect but make a breakdown on a Friday night look as bad as one at 7 a.m. on a Monday. If your crews work set shifts, count downtime against scheduled operating hours: downtime percentage is unplanned downtime hours divided by scheduled operating hours, times 100. The NIST survey of US manufacturers used the same idea, measuring unplanned downtime as a percentage of planned production time.
The fields every downtime record needs
A good downtime line is short enough that a technician fills it in on a phone at the machine, and complete enough that you can sort it six months later.
- Unit number, and the location or job site where it stopped
- Down timestamp, taken when the problem was reported rather than when the shop heard about it
- Return-to-work timestamp, taken when the machine was released to the operator
- Planned or unplanned
- Cause category: breakdown, damage, operator report, failed inspection, waiting on parts, waiting on vendor, scheduled PM
- Problem, cause and remedy codes on the repair that ended the outage
- The work order number, so cost and labor link to the same event
Split the outage into waiting and wrenching
On mobile equipment, the repair itself is often the shortest part of an outage. A hypothetical excavator fails at 9 a.m. on a site. The operator calls it in at 11, a mechanic arrives at 2, diagnoses a failed sensor, and the part lands two days later. The repair took 90 minutes; the machine was down for over 50 hours.
If your log records only the total, you will try to fix the wrong thing. Record status changes inside the outage: reported, diagnosed, waiting on parts, waiting on a vendor, in repair, released. Then the monthly review can say “we lose more hours to parts lead time than to repairs” and point to stocking decisions instead of technician speed. The DOE’s FEMP O&M guide lists shortest, median and longest times to close a work order by component among typical CMMS functions, and those spreads are where waiting time shows up.
Collecting the data without slowing people down
Paper downtime sheets fail in a predictable way: someone fills them in at the end of the week from memory, rounds every outage to a half day and leaves the reason blank. The fix is to capture the event where it happens. Let the operator or driver mark the machine down from a phone or a QR label when they report the problem, and let the technician’s first action on the repair mark it as being worked on in the shop.
Tie the status to the work order wherever you can. When starting the job and closing it change the machine’s status, the timestamps take care of themselves. For trucks under FMCSA rules there is a second reason to keep this tidy: 49 CFR 396.3 requires motor carriers to keep records of inspection, repairs and maintenance showing their date and nature, retained where the vehicle is housed or maintained “for a period of 1 year and for 6 months after the motor vehicle leaves the motor carrier’s control.” A downtime log tied to repair records covers part of that.
If you are still on paper or a spreadsheet, our equipment downtime tracker template gives you the columns to start with today.
Finding the causes worth fixing
Once a month, sort the log three ways: total downtime hours by machine, by cause category and by problem code, and read the top five lines of each sort first. NIST found that the quarter of surveyed manufacturers relying most on reactive maintenance had 3.3 times more downtime than the quarter relying least. If most of your hours come from unplanned breakdowns, start with the PM program on those units.
Look for the patterns that a total hides. One machine with ten short outages has a different problem from one with a single three-week outage. A cause category like “waiting on vendor” that keeps growing points to a contract or a turnaround issue. Repeated outages after a PM visit can mean the service itself is introducing faults.
Pick the top two or three causes, open a root-cause review for each, and check the same sort three months later to see whether their hours fell.
Common downtime tracking mistakes
Watch for the habits listed here, and audit a sample each month: pick five outages and check the timestamps against the work order and the operator’s report. Catching a wrong timestamp in the first month costs less than explaining a year of bad numbers.
- Starting the clock when the shop opens the work order instead of when the operator reported the problem
- Leaving machines marked down after they are back at work, which inflates the numbers and kills trust in them
- Mixing planned service hours into breakdown downtime
- Using a free-text reason field that nobody can count
- Counting idle machines as down, or broken machines nobody needed as available
Downtime tracking in FleetZap
FleetZap logs every change in a machine’s status (Available, Down or In service) with the time, the reason and the person who made it. In FleetZap, In service means the machine is being worked on in the shop. Operators can report a problem from a QR label, and technicians in the field app can mark the machine down in the same step they open the repair. Starting work on the work order moves the machine to In service, and completing the job sets it back to Available, so the down and in-service time per asset builds up without a separate log.
Each machine shows its 30-day availability and its own downtime history, and the downtime history exports to CSV. Repairs close with problem, cause and remedy codes, and the failure analysis report lists the top problems and repeat offenders over whatever period you pick. Set a downtime cost per hour on a category or a single machine and FleetZap prices each outage in dollars.
Key takeaways
- If parts and vendor waits add up to more hours than repair time for a machine type, review the spares you stock for it before you look at technician speed.
- Ask for a two-line written explanation on any single outage longer than a set limit, such as three shifts, while people still remember the details.
- If a cause’s hours haven’t fallen three months after a fix, reopen the root-cause review instead of adding another PM task.
- Sort downtime by machine model as well as by unit; a fault spread thinly across 20 identical loaders only shows up in the model total.
Free tools for this
- MTBF calculator: Mean time between failures, mean time to repair and availability
- OEE calculator: Overall equipment effectiveness from availability, performance and quality
- Weibull reliability calculator: Reliability at a given time, B10 life and mean life from Weibull shape and scale
- Uptime calculator: Downtime allowed per year, month, week and day at an uptime target, and your actual uptime
Sources
FleetZap Maintenance
Work orders, PM, parts, compliance, assets and KPIs. Explore FleetZap Maintenance.
Frequently asked questions
What is downtime tracking?
Downtime tracking is the practice of recording every period when a machine can’t work: when it stopped, when it returned, whether the stop was planned, and the cause. Over time the log shows which machines and which problems lose the most hours, and gives you the data for availability, MTTR and downtime cost.
How do you track machine downtime manually?
Use one line per outage on a sheet or spreadsheet with the unit number, down date and time, return-to-work date and time, hours down, planned or unplanned, cause and the repair done. Fill it in when the event happens rather than at the end of the week, and total hours by machine and by cause each month.
What are the main causes of equipment downtime?
For equipment fleets the usual causes are breakdowns from missed or late preventive maintenance, damage on the job, failed inspections, waiting for parts, waiting for an outside repair shop and operator-reported problems that sit unanswered. Your own log is the only reliable ranking, because the mix differs between a rental yard, a construction fleet and a municipal fleet.
Should planned maintenance count as downtime?
Track it, but keep it separate. Scheduled service takes a machine out of work, so it belongs in the log for planning purposes. Mixing it with breakdown downtime, though, hides the effect of the PM program. Report unplanned downtime as its own figure and planned service hours as another.
What is a good downtime percentage?
No single figure fits every fleet, because duty cycles, machine age and seasons differ. Compare each machine with its own history and with similar units in your fleet. A machine whose downtime keeps rising while its peers hold steady needs attention, whatever the absolute number.