FleetZap · Features · Solutions · FleetZap Maintenance · FleetZap Rentals · FleetZap Dispatch · FleetZap GPS Tracking · What a CMMS does · GPS tracking & engine hours · Dispatch & route optimization · Rentals module · Industries · Customers · Resources · Free calculators · Free templates · Pricing · Contact

What is OEE (overall equipment effectiveness)?

Updated · Reviewed by Israel Margulies, founder and CEO of High Point GPS

OEE, or overall equipment effectiveness, measures how much of a machine’s planned time turns into good output. You get it by multiplying three factors (availability, performance and quality) into one percentage. It was built for manufacturing lines that make countable parts; on mobile equipment you have to redefine performance and quality, and many fleets stop at availability.

OEE

Availability × Performance × Quality

A hypothetical press ran at 90% availability, 95% performance and 98% quality: 0.90 × 0.95 × 0.98 ≈ 83.8% OEE.

Free tool: OEE calculator: Overall equipment effectiveness from availability, performance and quality.

The three parts of OEE

Each factor looks at the time the machine was scheduled to work from a different angle.

  • Availability: of the planned time, how much was the machine running? Breakdowns, set-ups and waiting for parts reduce it.
  • Performance: while running, how fast did it produce compared with its ideal rate? Slow cycles and short stops reduce it.
  • Quality: of everything produced, how much was good the first time? Scrap and rework reduce it.

How to calculate OEE

Start by defining planned production time: the time the machine was supposed to be working, excluding planned breaks and times with no work scheduled. Availability is run time divided by planned time. Performance is actual output divided by what the machine would have produced at its ideal rate during that run time. Quality is good units divided by total units.

Multiply the three together. Because the factors multiply, modest losses compound: three factors of 90% each give about 73% OEE. Small losses spread across a shift can cost as much as one big breakdown, and OEE puts them on the same scale.

OEE for mobile equipment and fleets

For a production line, output is easy to count. For excavators, trucks or generators it often isn’t: an hour digging clay is not an hour digging rock, and nothing gets scrapped. Some fleets adapt the factors. On a hypothetical quarry haul truck with a target cycle of 6 loads an hour that averaged 5, performance would be about 83%, and quality could be the share of loads delivered at the right weight.

If you use OEE on mobile equipment, write the definitions down and keep them fixed, so you can compare this quarter’s figure with last quarter’s. Many fleets find that availability and utilization tell them most of what they need without the extra bookkeeping.

Improving OEE

Maintenance has the most direct influence on the availability factor. Fewer breakdowns, shorter repairs and services done at planned times all raise it. Performance losses often trace back to worn components, badly adjusted machines or operators working around a known fault, so preventive work helps there too. Quality losses usually need process fixes alongside maintenance.

You will see high OEE figures quoted as “world class”. Those figures depend on the industry and on how each factor is defined, so measure a machine against its own trend.

What FleetZap measures

FleetZap does not calculate OEE directly, because performance and quality depend on production data that lives outside a maintenance system. It covers the availability side in detail: every time a machine goes down or back in service the change is recorded with a reason, and Reports show availability, MTBF, MTTR, downtime cost and planned versus reactive work.

Meters come from hand entries, the field app or optional GPS telematics, so run time comes from real readings. You can export those figures as CSV and combine them with your production numbers to build a full OEE picture.

Key takeaways

  • Three factors at 90% each give only about 73% OEE, so hunt small losses as well as big ones.
  • On haul trucks and loaders, define performance as loads or tonnes per hour against a target cycle.
  • Write the factor definitions down before you report OEE, and don’t change them mid-year.
  • Worn parts and operators working around a known fault also cost you performance, which maintenance can win back.

Free tools for this

  • OEE calculator: Overall equipment effectiveness from availability, performance and quality
  • Uptime calculator: Downtime allowed per year, month, week and day at an uptime target, and your actual uptime
  • Downtime cost calculator: What an hour of a machine down really costs, per breakdown and per year
  • MTBF calculator: Mean time between failures, mean time to repair and availability

Sources

FleetZap Maintenance

Work orders, PM, parts, compliance, assets and KPIs. Explore FleetZap Maintenance.

Frequently asked questions

What is a good OEE score?

Compare a machine against its own history and against similar machines measured with the same definitions. A press and a haul truck can’t share a target, and two sites that count set-up time differently will report different OEE for identical work. Pick your definitions, record a baseline for a few months and set targets from there.

What is the difference between OEE and availability?

Availability is one of the three factors in OEE. It asks only whether the machine was running when it was supposed to be. OEE multiplies it by performance, how fast the machine ran, and quality, how much of its output was good. A machine can show high availability and a low OEE if it runs slowly or produces rework.

Can OEE be used for construction equipment?

It can, with adapted definitions such as tonnes moved or loads hauled per hour for performance and loads delivered to spec for quality. Many construction and rental fleets find availability, utilization and downtime cost easier to collect and more useful for day-to-day decisions, and they save OEE for a few production machines such as crushers or screening plants.

Is OEE the same as TEEP?

No. OEE measures effectiveness against planned production time. TEEP, total effective equipment performance, measures it against all calendar time, so it also shows how much of the day or week the machine was not scheduled at all. A machine working one shift can post a strong OEE and a low TEEP, which points to spare capacity.