FleetZap · Features · Solutions · FleetZap Maintenance · FleetZap Rentals · FleetZap Dispatch · FleetZap GPS Tracking · What a CMMS does · GPS tracking & engine hours · Dispatch & route optimization · Rentals module · Industries · Customers · Resources · Free calculators · Free templates · Pricing · Contact

Maintenance planning and scheduling explained

Updated · Reviewed by Israel Margulies, founder and CEO of High Point GPS

Maintenance planning and scheduling are two linked jobs. Planning works out how a job will be done: steps, parts, tools, skills and time. Scheduling decides when it will be done and by whom, based on who is available and when the machine can come out of service. With both in place, technicians start the day with a list of jobs that are ready to go.

Schedule compliance

Scheduled jobs completed as planned ÷ Jobs scheduled × 100

A hypothetical shop scheduled 50 jobs for a week and completed 42 as planned: 42 ÷ 50 = 84% schedule compliance.

Planning vs. scheduling

Planning answers what and how. A planned job has a clear scope, a procedure, a parts list, special tools, the skills needed and an estimate of hours. Scheduling answers when and who. It fits planned jobs into the available technician hours and the times machines are free.

Keeping them as separate steps buys you lead time. An excavator’s 2,000-hour service can be planned weeks before it is scheduled, with the filters, fluids and a replacement hydraulic hose ordered in the meantime, so when the slot comes everything is waiting on the bench.

What a well-planned job includes

A technician should be able to pick up a planned job and start work without hunting for information or parts.

  • The machine, where it is parked and the date operations can release it
  • The scope and the steps or procedure, such as the manufacturer’s service sheet for that hour mark
  • Parts and quantities, reserved or on hand: filters, fluids by the gallon, the seal kit
  • Special tools or outside help: a track press, a crane for a boom pin, a mobile line-boring contractor
  • Estimated labor hours and the skill needed, such as an electrician for a harness fault
  • Safety requirements such as lockout/tagout and blocking a raised boom

A weekly scheduling routine

Many shops use a simple weekly cycle. Near the end of the week, review the backlog of planned, ready-to-go jobs, confirm available technician hours for the next week, and agree with operations which machines can come out of service and when. Then size the week from your own breakdown record.

Here is the arithmetic for a hypothetical shop of 4 technicians on 40-hour weeks: 160 hours. Over the last 12 weeks, breakdowns and other unplanned jobs took an average of 38 hours a week. Schedule 160 − 38 = 122 hours of planned work, about 76% of the week, and leave the rest open. If breakdowns drop to 25 hours a week over the next quarter, raise the scheduled figure to 135.

During the week, assign jobs day by day and protect the schedule. When an urgent repair lands, the supervisor picks the scheduled job it bumps, moves that job to a named day and tells the operator or site waiting on it.

Measuring planning and scheduling

A few measures show whether the process is working. Schedule compliance is the share of scheduled jobs completed as planned. Estimate accuracy compares estimated with actual hours. The planned maintenance percentage shows how much of all maintenance time was planned, and backlog in weeks shows whether the workload is under control.

Record why each missed job slipped. Parts not arriving, machines not released and estimates that ran low each need a different fix.

Planning and scheduling in FleetZap

In FleetZap, work orders carry steps or an attached procedure, parts from inventory, a team and estimated hours, and the estimate can be filled from the median labor hours of similar past jobs. Preventive work orders open automatically from schedules, and upcoming services are projected from each machine’s daily use.

The calendar shows work by day, week or month, and you can drag a job onto a day to schedule it. The workload board shows each person’s planned hours against their capacity, with overdue and over-capacity filters, and you drag a card to reassign it. Teams, labor timers and Reports on backlog, PM compliance and planned versus reactive work close the loop.

Key takeaways

  • Plan a job weeks ahead and order its parts then; schedule it only once everything is in hand.
  • Agree on machine release dates with operations before you build the week, not after.
  • When urgent work arrives, name the scheduled job it displaces.
  • Compare estimated with actual hours on every job, so the next estimate is closer.

Free tools for this

Sources

FleetZap Maintenance

Work orders, PM, parts, compliance, assets and KPIs. Explore FleetZap Maintenance.

Frequently asked questions

Do small shops need a planner?

They need the planning work done, though rarely by a dedicated person. In a small shop the supervisor or lead technician often plans and schedules. What matters is that someone sets aside time each week to do it, instead of deciding everything on the spot. Blocking a fixed half-day on the calendar for planning is a common way to protect that time when the shop is busy.

How far ahead should maintenance be scheduled?

Many teams schedule one week at a time in detail and look a few weeks further ahead for major services and parts orders. Preventive services that depend on meter readings can be projected from each machine’s usage. Long-lead items, such as an undercarriage or an engine for a rebuild, need planning months ahead of the slot.

How much time should be left for breakdowns?

Leave about as many hours open as your unplanned work has averaged lately. A hypothetical shop that lost 38 hours a week to breakdowns over 12 weeks schedules 122 of its 160 hours and keeps the rest free. As planned work grows and breakdowns fall, schedule more. Recheck monthly, because a busy season can double the breakdown load.