FleetZap · Features · Solutions · FleetZap Maintenance · FleetZap Rentals · FleetZap Dispatch · FleetZap GPS Tracking · What a CMMS does · GPS tracking & engine hours · Dispatch & route optimization · Rentals module · Industries · Customers · Resources · Free calculators · Free templates · Pricing · Contact

What is planned maintenance percentage (PMP)?

Updated · Reviewed by Israel Margulies, founder and CEO of High Point GPS

Planned maintenance percentage, often shortened to PMP, is the share of maintenance hours spent on planned work out of all maintenance hours. A low PMP means breakdowns set most of the week’s work. As it rises, workloads steady and fewer repairs start with a crew waiting on the machine.

PMP

Planned maintenance hours ÷ Total maintenance hours × 100

A hypothetical shop logged 600 maintenance hours last quarter, 420 of them on planned work: 420 ÷ 600 = 70% PMP.

How PMP is calculated

Add up the hours spent on planned maintenance in a period and divide by the total maintenance hours in the same period. Hours are better than work order counts, because one engine rebuild and one wiper blade are both a single work order but very different amounts of effort.

If you do not track hours yet, a count of work orders is a reasonable starting point. Expect the figure to shift once technicians record real labor time.

What counts as planned work

Planned work is anything scheduled before it had to be done. The line between planned and unplanned is where most arguments start, so agree on it up front.

  • Planned: preventive services, inspections, and repairs found early and scheduled ahead
  • Planned: condition-based jobs triggered by readings before a failure
  • Unplanned: breakdowns and repairs that interrupt the day’s schedule
  • Unplanned: urgent jobs added to the schedule after it was set
  • A simple test many teams use: was the job on the schedule before the week started?

PMP vs. PM compliance

PM compliance asks whether scheduled preventive jobs were done on time. PMP asks how much of all maintenance effort was planned in the first place. A team can finish every PM on time and still have a low PMP if breakdown repairs take most of the technician hours.

Read them together: compliance tells you whether the shop does what it planned, and PMP tells you whether enough of its work gets planned.

How to raise your PMP

PMP goes up when defects are found before they become breakdowns and when found defects are scheduled instead of fixed on the spot. NASA’s maintenance guide aims for 70% of labor hours on preventive and condition-based work, and the US Department of Energy notes that top-performing facilities keep reactive work under 10%. Both come from facility maintenance, so measure a fleet against its own starting point.

  • Add daily operator checks so small problems are reported early
  • Use inspection steps with pass/fail items and readings instead of a bare “looks OK”
  • Turn found defects into scheduled work orders with parts ready
  • Set PM intervals by real usage so services are neither late nor wasted
  • Review breakdowns monthly and adjust PMs for repeat failures

Tracking planned vs. reactive work in FleetZap

FleetZap reports planned versus reactive work alongside PM compliance, backlog, MTBF and MTTR. Work orders have types (repair, preventive and inspection), and technicians record labor with timers on their phones, so the figures come from real hours. Labor by person is also reported.

Defects found during inspections or pre-use checks open repair work orders automatically. You can schedule those on the calendar and assign them to people with capacity on the workload board, which moves the hours from the reactive column to the planned one.

Key takeaways

  • No labor data yet? Start with work order counts, then switch to timer hours and expect the figure to move.
  • A defect found on Tuesday and fixed on the spot counts as unplanned; logged, parted and booked for Thursday, it counts as planned.
  • Decide in writing where an urgent job added mid-week falls before you report the first figure.
  • When PMP stalls, look at repeat failures first: they are breakdowns you could have scheduled.

Free tools for this

Sources

FleetZap Maintenance

Work orders, PM, parts, compliance, assets and KPIs. Explore FleetZap Maintenance.

Frequently asked questions

What is a good planned maintenance percentage?

It depends on how strictly you define planned work. A shop moving from mostly reactive work sees its biggest gains in the first year, long before it reaches any published benchmark. Track your own figure each quarter and aim for it to rise while breakdown hours fall, so you know the gain is real.

Is a found defect that I fix immediately planned or unplanned?

Most teams count it as unplanned if it interrupted the schedule, even though it was found during an inspection. If it was logged, parted and scheduled for a later slot, it counts as planned. Pick one rule and apply it consistently.

Can PMP be too high?

In theory, yes: if everything is planned, you may be over-servicing some machines. In practice most fleets are far from that point. If PMP is high but costs are rising, review whether some preventive tasks can be done less often or replaced by condition checks.

How long does it take to improve PMP?

It varies with how reactive the shop is today. Adding operator checks and scheduling found defects can show results within a few months, because those changes move work from one column to the other right away. Deeper gains, from better intervals and fewer repeat failures, usually build over a year or more as the failure history grows.