What is planned maintenance and how do you build a program?
Updated · Reviewed by Israel Margulies, founder and CEO of High Point GPS
Planned maintenance is any maintenance work that is scheduled, scoped and prepared before it starts: parts ordered, procedure ready, technician assigned. It covers preventive services, inspections and known repairs, as opposed to unplanned work that interrupts the day when something breaks.
Planned vs preventive maintenance
The two terms overlap. Preventive maintenance is work done on a schedule to prevent failure. Planned maintenance covers any job prepared in advance, so a cracked hose found on Monday’s inspection and booked for Tuesday, with the hose on order, is planned work that isn’t preventive.
Steps to build a planned maintenance program
The asset list comes first because every interval, procedure and cost attaches to a machine record. Start with the machines that stop a job when they fail, run their schedule for a month or two, and add the next group once those services close on time.
A hypothetical wheel loader shows the rest of the steps. Its manual calls for a service every 500 hours or 6 months, whichever comes first. It reads 4,620 hours and averages 8 hours a working day, so the 5,000-hour service is about 47 working days away, inside the 6-month limit. Two weeks before, the planner checks the kit: engine oil and filter, fuel filters, an air filter element. One fuel filter is out of stock, so it goes on order now instead of on the morning of the job. The work order gets the procedure, an estimate of 4 hours and a technician, and the loader’s operator knows which morning it stays in the yard.
- List every machine with make, model, serial and meter
- Enter service intervals from the manufacturer’s manuals
- Write a procedure for each service type
- Keep meter readings current so meter-based services come due on time
- Assign each job to a person or team with an estimate of hours
- Each month, list the services that went undone and why
Scheduling by meter and calendar
Equipment wears with use, so most services run on engine hours or miles. Hoses, batteries, fluids and safety inspections age whether the machine works or not, so they need a calendar interval too. Set both, every 500 hours or 6 months for example, and do the service at whichever limit comes first. A machine parked all winter still gets its fluids checked, and a machine working double shifts doesn’t wait for a date.
Preparing the work
Before the job day, the technician should know which machine, where it is, the procedure, the parts and roughly how long it will take. A parts check a week or two ahead removes the most common delay. If a loader already has a repair booked for Thursday and its service is due the following week, do both on Thursday and park it once.
Running planned maintenance in FleetZap
In FleetZap, one schedule can carry a meter interval, a calendar interval or both, and it can cover one machine, a whole category or a picked list. Work orders open automatically with the procedure attached, and upcoming services are projected from each machine’s daily use so you can see what is coming.
The calendar shows work, PM projections and rentals by day, week or month, and the workload board compares assigned hours with each person’s capacity. Estimated hours are suggested from similar past jobs, and the spare-parts list on each machine shows live stock.
Key takeaways
- A repair found on inspection and booked with parts ordered counts as planned work, even though it isn’t preventive.
- Give anything that ages while parked (hoses, batteries, fluids) a calendar limit next to its hour interval.
- Work out the due date from average daily hours, then check the parts kit two weeks before.
- If services go undone each month, shrink or re-time the schedule until your team can close it.
Free tools for this
- Next PM due calculator: When the next service comes due, in hours and on the calendar
- MTBF calculator: Mean time between failures, mean time to repair and availability
- OEE calculator: Overall equipment effectiveness from availability, performance and quality
- Uptime calculator: Downtime allowed per year, month, week and day at an uptime target, and your actual uptime
Sources
FleetZap Maintenance
Work orders, PM, parts, compliance, assets and KPIs. Explore FleetZap Maintenance.
Frequently asked questions
How far ahead should maintenance be planned?
Work on two horizons. In a hypothetical shop, the planner builds next week’s schedule every Thursday: eight services coming due, two repairs whose parts have arrived, and the total hours checked against crew capacity. A rolling view of the next few months covers big jobs, like an undercarriage, so parts are ordered early. Meter-based due dates come from each machine’s average daily use.
What should a planned maintenance work order include?
At minimum: the machine, the task, a procedure or checklist, the parts needed, an assigned person or team, a due date and an estimated time. After completion it should record actual hours, parts used, meter reading and any problems found for follow-up.
How do I know if my planned maintenance program is working?
Track PM compliance, the share of planned versus reactive work, backlog and downtime month by month. On-time services and falling breakdowns mean it works. PMs that keep running late mean the schedule is larger than your crew can handle.