FleetZap · Features · Solutions · FleetZap Maintenance · FleetZap Rentals · FleetZap Dispatch · FleetZap GPS Tracking · What a CMMS does · GPS tracking & engine hours · Dispatch & route optimization · Rentals module · Industries · Customers · Resources · Free calculators · Free templates · Pricing · Contact

What is PM compliance?

Updated · Reviewed by Israel Margulies, founder and CEO of High Point GPS

PM compliance is the percentage of preventive maintenance work orders completed on time out of those that came due in a period. When it slips, breakdowns tend to follow, which is why many shops put it at the top of their weekly report. Agree on the definition and the grace window first, or the team will argue about the number instead of acting on it.

PM compliance

PM work orders completed on time ÷ PM work orders due × 100

A hypothetical fleet had 40 PMs due in March and finished 34 within the grace window: 34 ÷ 40 = 85% PM compliance.

How PM compliance is calculated

Count the preventive work orders that came due in the period, then count how many of them were completed on time. Divide the second by the first. Work orders that were canceled for a good reason (the machine was sold, for example) are usually removed from both counts.

Keep it to preventive work. Mixing in repairs or projects makes the number harder to read and hides whether the service program itself is being followed.

Setting a grace window

A PM done one day late is not the same as one done a month late, so many teams allow a grace window. A commonly cited approach for calendar-based PMs is a window of about 10% of the interval (roughly three days on a monthly service). Whatever you pick, write it down so the number means the same thing every month.

Meter-based services need a meter window, such as a set number of engine hours past due. Check your window against the manufacturer’s guidance where warranty coverage depends on service intervals.

Why PM compliance falls

A falling number is a symptom. These are the usual causes, each with its own fix.

  • Too many PMs for the technician hours available: compare the PM hours coming due with capacity, spread services across weeks or add hours
  • Machines are out on jobs when services come due: send a technician to the site or line the service up with the machine’s next transfer to the yard
  • Parts or kits are not ready when the work order opens: pre-stage filters and fluids a week ahead
  • Intervals are set so short that jobs feel optional: go back to the manufacturer’s interval or set it by real usage
  • Work is done but not closed in the system: have technicians close the order on their phone before they leave the machine

Raising PM compliance

Put preventive work on the same calendar as repairs and projects. Look a few weeks ahead and group services for machines that come back to the yard together.

Review missed PMs each week and tag each one with a cause from the list above. After a month the tags show whether you need capacity, scheduling or different intervals. Pair compliance with breakdown counts: if services are on time and breakdowns stay flat, the PMs are checking the wrong things.

PM compliance in FleetZap

FleetZap reports PM compliance in Reports from your real work orders. Preventive schedules can run by meter (engine hours or miles) and by calendar, whichever comes first, for a single machine, a whole category or a picked list of units. Work orders open automatically with the procedure attached, and upcoming services are projected from each machine’s daily use so you can plan ahead on the calendar.

The workload board shows planned hours against each person’s capacity, and the health score of a machine drops when its PM is due or overdue. Open and overdue work is also listed in the weekly summary email.

Key takeaways

  • Remove canceled PMs (a sold machine, for example) from both the due and the completed counts.
  • Write the grace window down: days for calendar PMs, engine hours or miles for meter PMs.
  • Tag every missed PM with a cause; the most common tag tells you what to fix first.
  • Count a PM finished after the grace window as missed, and track late completions on their own.

Free tools for this

  • USDOT and MC number lookup: A carrier’s legal name, status, operation, fleet size, safety rating and MCS-150 date from FMCSA data
  • Next PM due calculator: When the next service comes due, in hours and on the calendar
  • MTBF calculator: Mean time between failures, mean time to repair and availability
  • OEE calculator: Overall equipment effectiveness from availability, performance and quality

Sources

FleetZap Maintenance

Work orders, PM, parts, compliance, assets and KPIs. Explore FleetZap Maintenance.

Frequently asked questions

What is a good PM compliance rate?

Figures around 90% are often cited as a target. Your grace window changes what that means: 90% inside a three-day window is a tighter standard than 90% inside a week. Set your own target from a few months of data, then raise it as you fix the causes of the misses.

Should late PMs count as compliant if they were eventually done?

Usually not. The measure exists to show timeliness, so most teams count a PM as compliant only if it was completed inside the due date plus the agreed grace window. Track late completions as a separate figure: a PM done two weeks late still got done, and the gap between late and never tells you whether the problem is capacity or access.

How is PM compliance different from schedule compliance?

PM compliance looks only at preventive work orders. Schedule compliance looks at all work that was scheduled for a period, including planned repairs, and asks how much of it was done as planned. A shop can hit every PM and still miss its schedule if planned repairs keep getting bumped by breakdowns, so many shops report both side by side.

Does PM compliance guarantee fewer breakdowns?

No. It measures whether services happen on time. Whether they are the right services at the right interval is a separate question. If compliance is high and breakdowns are not falling, read the failure codes on recent repairs and add checks for the faults your PMs keep missing.